<h1>江西省配煤中心加快建设</h1>
	<div class="v2_comtent_info01">
	<span>2013-5-6 14:03:31</span>来源:<span>煤炭</span>作者:<span></span>
	</div>
	<div class="v2_comtent_info02"><a title="投稿" class="v2_content_ico01">投稿</a><a title="打印" class="v2_content_ico02">打印</a><a title="收藏" class="v2_content_ico03">收藏</a>
	<!-- Baidu Button BEGIN -->
    
    <div id="bdshare" class="bdshare_t bds_tools get-codes-bdshare">
		<span class="bds_more">分享到:</span>
		<a class="bds_qzone"></a>
		<a class="bds_tsina"></a>
		<a class="bds_tqq"></a>
		<a class="bds_renren"></a>
	</div>
    </div>
	<script type="text/javascript" id="bdshare_js" data="type=tools&amp;uid=684790" ></script>
	<script type="text/javascript" id="bdshell_js"></script>
	<script type="text/javascript">document.getElementById("bdshell_js").src = "http://bdimg.share.baidu.com/static/js/shell_v2.js?cdnversion=" + new Date().getHours();</script>
	<!-- Baidu Button END -->
	<div class="v2_comtent_info03">
		<ul>
			<li><b class="v2_content_ico04">导读:</b></li>
			<li>庐山区城东港区的省配煤中心项目建设工地</li>
		</ul>
		<ul>
			<li><b class="v2_content_ico05">关键字:</b></li>
			<li>配煤 江西省配煤中心</li>
		</ul>
		<div class="clear_hu"></div>
	</div>
	<div class="over_x"><p>近日,记者来到位于庐山区城东港区的省<b>配煤</b>中心项目建设工地,忙碌的建设场景尽收眼底,工作人员正抓紧安装设备。据项目相关负责人介绍,为确保项目顺利推进,项目方在资金上优先保障,并制定工程进度表,对每道工序作出细致安排。<br />
  <br />
  目前,配煤公用码头已完成70%,货场正在进行土方平整,预计9月底土建竣工;配煤专用码头已完成80%,正在进行设备安装,预计9月份完工;配煤堆场建设有序推进,储煤区正在夯实,项目预计2014年5月份全面完工。</p>
<p>(关键字:配煤 江西省配煤中心)</p></div>